Progress of Baan Plai Haad Pattaya

Jul 2014 

Project progress of Baan Plai Haad Pattaya

 The construction works of the concrete skeleton of Baan Plai Haad Pattaya from Bangkok developer Sansiri reached the 26th of the 31th floors. In this way, the percentage of completion of this stage of the works close to 90%.


 

 

From the report of  general project contractor representative manager of Bangkok Home Construction Co. Ltd., works are carried out in accordance with the approved schedule and initially, so completion of the project as announced earlier, is scheduled for 2015, March.

 

 

An  installation of pipe system in the walls completed on a few floors. In the process of installing plumbing and electrical system between the buildings.

 

 

 Masonry-reinforced plaster-skim works, 
tiling works on the floors in the process.  Masonry and Plastering woks in some residential units are fully completed. Interior precast architectural works has started on the floors.

 

 